Melbourne data centre expansion halted as power delays and community opposition bite

NEXTDC has paused every project without a signed customer after residents in Melbourne's west stopped the power upgrade its West Footscray site needs. Its chief executive says the company has to win back trust first.

Large high-voltage transformers and steel gantries at an electricity terminal station, seen through a wire fence across a grassy field.
Transformers at Keilor Terminal Station, which steps power down to 66,000 volts for Melbourne's northern and western suburbs. NEXTDC's West Footscray site is waiting on an upgrade to the same kind of 66kV network. File photo. Photo: Allalone89 / Public domain

One of Australia's biggest data centre companies has put the brakes on its growth after a fight with residents in Melbourne's inner west left its flagship West Footscray site short of power.

NEXTDC said on Monday it would pause all projects that do not have a customer contract, Reuters reported. Chief executive Craig Scroggie told a UBS investor conference the company "certainly didn't expect to be in the position we're in today", and linked the problem to public unease about artificial intelligence and data centres, which he described as an issue of "social license".

"That work can't restart until we clearly communicate that we've solved this problem," he said, adding that winning community support for the Melbourne site is now the top priority.

What went wrong in West Footscray

NEXTDC's M3 data centre sits about 10 kilometres west of the CBD and is planned to grow to 225 megawatts. To get more power, it needs electricity distributor Jemena to upgrade the local 66,000-volt network.

In September, Jemena stopped installing 15-metre power poles in neighbouring Yarraville after residents protested, with some leaving cars and bins out to block work crews, the ABC reported. Jemena cited community and stakeholder opposition, safety concerns and limited site access, and the local council has not given consent as road authority while consultation continues, according to NEXTDC. Jemena does not expect to resume before February 2027.

Residents have long raised concerns about diesel fumes and noise from the site, which they say is just 15 metres from homes. "NextDC M3 doesn't have social licence for the existing building, they certainly don't have it for an expansion," said Sean Brown, a founding member of residents' group Citizens of Tottenham. The group's president, Jacqui Glover, said the delay was "a reminder that the people living beside these developments cannot simply be pushed aside."

The money

Revenue forecast
Cut to A$475–500 million for 2026-27, from A$615–640 million
Earnings forecast
Cut to A$245–265 million, from A$385–410 million
Share price
Down about 42 per cent after the October warning, since recovered
Building budget
A$4.5–5 billion this financial year, down from A$5.25–5.75 billion
New shareholders
Rivals Goodman Group and Digital Realty bought a 9.9 per cent stake for about A$715 million

Goodman and Digital Realty said they had no current plans to make a takeover offer but reserved the right to do so. NEXTDC says construction is continuing inside the existing West Footscray buildings and the affected capacity is still under contract to an unnamed customer.

Where the election comes in

NEXTDC has applied to the Victorian Government to expand the site. The company says a decision on that permit is now expected in 2027 because of caretaker rules ahead of the 28 November state election. Victoria has also announced rules to keep new data centres at least 150 metres from homes and schools, the ABC reported.

NEXTDC is due to report the outcome of a review of its building plans at its annual general meeting on 20 November.